`56` workers can finish a piece of work in `14` days. If the work is to be completed in `8` days, then how many extra w

Ask a Question


Question Asked by a Student from EXXAMM.com Team


Q 1615267169.     `56` workers can finish a piece of work in `14` days. If the work
is to be completed in `8` days, then how many extra workers
are required `?`
IBPS-CLERK 2013 Mains 14/12/2013
A

`36`

B

`48`

C

`44`

D

`42`

E

`32`

HINT


Solution
(Provided By a Student and Checked/Corrected by EXXAMM.com Team)