2 men or 3 women or 6 boys can finish a work in 480 days, then the number of days taken by 4 men, 4 women and 4 boys to

Ask a Question


Question Asked by a Student from EXXAMM.com Team


Q 2424791651.     2 men or 3 women or 6 boys can finish a work in 480 days, then the number of days taken by 4 men, 4 women and 4 boys to finish the work is
IBPS-CLERK 2017 Mains
A

86 days

B

120 days

C

72 days

D

160 days

E

None of these

HINT


Solution
(Provided By a Student and Checked/Corrected by EXXAMM.com Team)