Q 2442745633.     A contract on construction job specifies a penalty for
delay in completion of the work beyond a certain date
is as follows: `Rs 200` for the first day, `Rs250` for the second
day, `Rs 300` for the third day etc., the penalty for each
succeeding day being `Rs 50` more than that of the
preceding day. How much penalty should the
contractor pay if he delays the work by 10 days?
IAS 2011 Prelims
A

`Rs 4950`

B

`Rs 4250`

C

`Rs 3600`

D

`Rs 650`

HINT


Solution
(Provided By a Student and Checked/Corrected by EXXAMM.com Team)

Find instant solution to any question from our database of 1.5 Lakh + Questions

 


Access free resources including

  • 100% free video lectures with detailed notes and examples
  • Previous Year Papers
  • Mock Tests
  • Practices question categorized in topics and 4 levels with detailed solutions
  • Syllabus & Pattern Analysis

Engineering


Medical


Banking


DEFENCE


SSC


RRB


CBSE-NCERT


OLYMPIAD