A, B and C together can complete 50% of the work in 2 days. All 3 starts to work but after 2 days B get sick and leave t

Ask a Question


Question Asked by a Student from EXXAMM.com Team


Q 2237445382.     A, B and C together can complete 50% of the work in 2 days. All 3 starts to work but after 2 days B get sick and leave the work. A and C complete the 1/6 of the work the next day and then A quits his job. The remaining work is done by C in 8 days. In how many days can A alone complete the work?
IBPS-PO 2017 Mock Mains
A

10 days

B

6 days

C

12 days

D

8 days

E

None of these

HINT


Solution
(Provided By a Student and Checked/Corrected by EXXAMM.com Team)

Find instant solution to any question from our database of 1.5 Lakh + Questions

 


Access free resources including

  • 100% free video lectures with detailed notes and examples
  • Previous Year Papers
  • Mock Tests
  • Practices question categorized in topics and 4 levels with detailed solutions
  • Syllabus & Pattern Analysis

Engineering


Medical


Banking


DEFENCE


SSC


RRB


CBSE-NCERT


OLYMPIAD