`12` machines can complete a work in `9` days. How many additional machines are to be deployed to finish the work in `

Ask a Question


Question Asked by a Student from EXXAMM.com Team


Q 2211423329.     `12` machines can complete a work in `9` days. How many
additional machines are to be deployed to finish the work in
`3` days?
IBPS-CLERK 2017 Mock Prelims
A

`36`

B

`27`

C

`24`

D

`16`

E

None of these

HINT


Solution
(Provided By a Student and Checked/Corrected by EXXAMM.com Team)