A and B can do a piece of work in 10 days, B and C in 12 days, and A and C in 15 days. How long would B take to do the

Ask a Question


Question Asked by a Student from EXXAMM.com Team


Q 2271767626.     A and B can do a piece of work in 10 days, B and C in 12 days,
and A and C in 15 days. How long would B take to do the
same work?
IBPS-CLERK 2017 Mock Prelims
A

40 days

B

24 days

C

8 days

D

`17 1/7` days

E

None of these

HINT


Solution
(Provided By a Student and Checked/Corrected by EXXAMM.com Team)