Q 2214645559.     `3` men & `4` women finish `25%` of work in `4` days while `8` men & `15` women can finish the whole work in `5` days. In how many days will `13` women finish it?

IBPS-PO 2017 Mock Prelims
A

`16` days

B

`24` days

C

`36`days

D

`48` days

E

None of these