Q 2216391270.     Deepak can do a piece of work in 25 days and Ashok can do
the same work in 40 days. They work together for 5 days
and then Deepak goes away. In how rnany days will Ashok
finish the remaining work?

IBPS-CLERK 2017 Mock Prelims
A

28

B

24

C

25

D

20

E

None of these