Q 2234134952.     A contractor decided to build a Dam in `75` days. He employed `225` men at the beginning and another `120` men after `25` days and completed the work in the stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?

IBPS-PO 2017 Mock Prelims
A

`30 3/8 ` days

B

`42 5/7 ` days

C

`35 3/8 ` days

D

`26 2/3 ` days