Q 2283780647.     A and B together can complete a piece of work in 16 days.
B alone can complete the same work in 24 days. In how
many days can A alone complete the same work?

IBPS-CLERK 2017 Mock Prelims
A

`34`

B

`50`

C

`48`

D

`42`

E

None of these