Q 2441767623.     50 men or 80 women can finish a job in 50 days. A
contractor deploys 40 men and 48 women for this
work, but after every duration oflO days, 5 completed.
The work is completed in

IAS 2004 Prelims
A

45 days

B

50 days

C

54 days

D

62 days